| Item | Amount |
|---|---|
| Material and equipment (from takeoff, page 3) | $43,914 |
| Waste factor, 8% on duct, flex and insulation ($8,547) | $684 |
| Sales tax on material + waste, 7% sample rate (permit, crane and TAB not taxed) | $2,691 |
| Labor, 276.8 hrs at $105/hr loaded | $29,064 |
| Direct cost | $76,353 |
| Overhead, 12% | $9,162 |
| Profit, 10% | $8,552 |
| Bid total, Division 23 HVAC | $94,067 |
All prices on this page are sample prices. On real jobs, labor rate, sales tax, overhead and profit are set to your numbers. You get the Excel file with live formulas, so you can change any rate and the total updates.
| Color / mark | Meaning | Measured |
|---|---|---|
| ━ heavy blue / ┅ heavy red | Supply mains / return mains, galvanized rectangular | 860 LBS / 420 LBS |
| ─ thin blue / ┄ thin red | Flex runouts: 8" and 6" supply / 12" return | 220 + 50 LF / 70 LF |
| ⊠ SD-1 / SD-2 · ▯ LD-1 | Supply diffusers 24x24 / 12x12 / linear slot | 15 / 4 / 3 |
| ▤ RG-1 | Return grilles, 24x24 perforated | 7 |
| ┃ damper bar | Opposed-blade volume dampers in mains (spin-in dampers at all 22 outlets) | 4 / 22 |
| EF · T | Exhaust fans with 6" duct to roof / thermostats | 2 + 30 LF / 2 |
| ┈ green / ● yellow tags | Condensate drain to roof drain / takeoff line numbers, matching page 3 | 60 LF / 20 tags |
Drawing simplified for this sample. On real jobs we mark up your actual PDF sheets and deliver them with the estimate.
| CSI | Description · plan reference | Qty | Unit | Material | Hrs | Labor |
|---|---|---|---|---|---|---|
| EQUIPMENT | ||||||
| 23 74 13 | RTU-1, -2: 5-ton packaged gas/electric RTU, 2,000 CFM, economizer · M-1 · tag 1 | 2 | EA | $19,700 | 28 | $2,940 |
| 23 74 13 | Roof curb, 14" insulated, with duct transition · M-1 · tag 2 | 2 | EA | $2,300 | 12 | $1,260 |
| 01 54 19 | Crane and rigging, 1 day with operator · — | 1 | LS | $2,600 | 8 | $840 |
| DUCTWORK & INSULATION | ||||||
| 23 31 13 | Supply mains, galv. rectangular, 24x12 to 12x8, with fittings · M-1 · tag 4 | 860 | LBS | $3,741 | 56 | $5,880 |
| 23 31 13 | Return mains, galv. rectangular, 22x14 to 16x10, with fittings · M-1 · tag 5 | 420 | LBS | $1,827 | 27.4 | $2,877 |
| 23 31 16 | Flex duct, 8" insulated R-8, runouts to SD-1, LD-1 · M-1 · tag 6 | 220 | LF | $924 | 11 | $1,155 |
| 23 31 16 | Flex duct, 6" insulated R-8, runouts to SD-2 · M-1 · tag 7 | 50 | LF | $170 | 2.6 | $273 |
| 23 31 16 | Flex duct, 12" insulated R-8, return drops to RG-1 · M-1 · tag 8 | 70 | LF | $427 | 4.2 | $441 |
| 23 33 13 | Spin-in collar with volume damper, one per outlet · M-1 · tag 9 | 22 | EA | $528 | 8.8 | $924 |
| 23 33 13 | Opposed-blade volume damper, in mains · M-1 · tag 10 | 4 | EA | $580 | 4 | $420 |
| 23 07 13 | Duct wrap, 2" FSK R-6, supply + return mains · M-1 · tag 11 | 1,080 | SF | $1,458 | 32.4 | $3,402 |
| 23 31 13 | Hangers, sealant, accessories allowance · — | 1 | LS | $640 | 0 | $0 |
| AIR DISTRIBUTION | ||||||
| 23 37 13 | SD-1, 24x24 lay-in square diffuser, 4-way, 8" neck · M-1 · tag 13 | 15 | EA | $1,230 | 12 | $1,260 |
| 23 37 13 | SD-2, 12x12 square diffuser, 6" neck · M-1 · tag 14 | 4 | EA | $224 | 3.2 | $336 |
| 23 37 13 | LD-1, linear slot diffuser, 2-slot, 4 ft, with plenum · M-1 · tag 15 | 3 | EA | $705 | 4.8 | $504 |
| 23 37 13 | RG-1, 24x24 perforated lay-in return grille, 12" neck · M-1 · tag 16 | 7 | EA | $518 | 5.6 | $588 |
| EXHAUST | ||||||
| 23 34 23 | EF-1, -2: ceiling exhaust fan, 110 CFM, backdraft damper · M-1 · tag 17 | 2 | EA | $590 | 6 | $630 |
| 23 31 13 | Exhaust duct, 6" round galvanized, fan to roof · M-1 · tag 18 | 30 | LF | $255 | 3.6 | $378 |
| 23 34 23 | Roof cap, 6", with damper and flashing · M-1 · tag 19 | 2 | EA | $270 | 3 | $315 |
| PIPING & CONTROLS | ||||||
| 23 21 13 | Condensate drain, 1" PVC sch 40, trap, to roof drain · M-1 · tag 20 | 60 | LF | $228 | 7.2 | $756 |
| 23 09 33 | Thermostat, 7-day programmable, with remote sensor · M-1 · tag 21 | 2 | EA | $620 | 4 | $420 |
| 23 09 33 | Thermostat cable, 18/8 plenum rated · M-1 · tag 22 | 260 | LF | $169 | 5 | $525 |
| GENERAL | ||||||
| 02 41 19 | Demo existing ductwork, diffusers; disconnect RTUs · — | 1 | LS | $0 | 18 | $1,890 |
| 23 05 93 | Test, adjust and balance, certified TAB agency (sub) · — | 1 | LS | $2,850 | 4 | $420 |
| 23 05 00 | Startup, charge check, filters, owner instruction · — | 1 | LS | $180 | 6 | $630 |
| 01 54 00 | Scissor lift rental, 1 week · — | 1 | LS | $480 | 0 | $0 |
| 01 41 26 | Permit allowance (verify with local fee schedule) · — | 1 | LS | $700 | 0 | $0 |
| Totals | $43,914 | 276.8 | $29,064 | |||
Sample prices. Labor at $105/hr loaded. Waste, sales tax, overhead and profit are added on page 1. Tag numbers point to sheet M-1, page 2.
| Step | What happens |
|---|---|
| 1. Send your plans | Email PDF drawings and specs to bids@squareandlevelfl.com and include your bid due date. |
| 2. Fixed quote in 2 hours | We reply with the price and delivery time before any work starts. |
| 3. Estimate delivered | Marked-up sheets, takeoff and Excel estimate, usually within 24–48 hours. |
| 4. One revision included | Tell us what changed and we update the numbers. |
This is a sample created to show our format. The project, quantities and prices are illustrative, not a client job or a quote.