| Item | Amount |
|---|---|
| Material (from takeoff, page 3) | $45,229 |
| Waste factor, 5% on framing, ceilings + accessories (board waste is already in the sheet counts) | $1,845 |
| Sales tax on material, 7% (sample rate) | $3,295 |
| Labor, 871.5 hrs at $82/hr loaded | $71,463 |
| Equipment, 19 ft scissor lift, 2 weeks | $1,300 |
| Direct cost | $123,132 |
| Overhead, 10% | $12,313 |
| Profit, 10% | $13,545 |
| Bid total, Division 09 framing, drywall + ceilings | $148,990 |
Prices shown are sample prices. On every real job, the labor rate, sales tax, overhead and profit are set to your numbers. You get the Excel file with live formulas, so you can change any rate and the total updates.
| Color / mark | Partition type · construction | Measured |
|---|---|---|
| ━ red · A | 3-5/8" 20ga to deck, 5/8" Type X each side, sound batts (demising, IT) | 184 LF |
| ━ blue · B | 3-5/8" 25ga to 6" above ceiling, 5/8" Type X each side, sound batts | 298 LF |
| ━ green · C | 2-1/2" 25ga to 6" above ceiling, 5/8" Type X each side, no insulation | 64 LF |
| ━ purple · D | 3-5/8" 20ga to deck, 5/8" MR wet side, sound batts (restrooms) | 56 LF |
| ┅ orange · E | 7/8" hat channel furring at exterior wall, 5/8" Type X one side | 160 LF |
| ▨ blue hatch / ▭ tan | Drywall ceiling (restrooms) / drywall soffit (reception); grid = ACT | 384 / 160 SF |
| ● yellow tags | Takeoff items, matching the plan references on page 3; yellow band = Level 5 walls | 11 tags |
Drawing simplified for this sample. On real jobs we mark up your actual PDF sheets and deliver them with the estimate.
| CSI | Description · plan reference | Qty | Unit | Material | Hrs | Labor |
|---|---|---|---|---|---|---|
| METAL STUD FRAMING · 09 22 16 | ||||||
| 09 22 16 | Type A · 3-5/8" 20ga studs @ 16" o.c., to deck, 14'-0" · A-101 · red · tag 1 | 184 | LF | $2,282 | 31.5 | $2,583 |
| 09 22 16 | Type B · 3-5/8" 25ga studs @ 16" o.c., 9'-6" (6" above clg) · A-101 · blue · tag 2 | 298 | LF | $1,520 | 30 | $2,460 |
| 09 22 16 | Type C · 2-1/2" 25ga studs @ 16" o.c., 9'-6" · A-101 · green · tag 3 | 64 | LF | $262 | 6 | $492 |
| 09 22 16 | Type D · 3-5/8" 20ga studs @ 16" o.c., to deck, wet walls · A-101 · purple · tag 4 | 56 | LF | $694 | 9.5 | $779 |
| 09 22 16 | Type E · 7/8" hat channel furring @ 16" o.c., exterior · A-101 · orange · tag 5 | 160 | LF | $688 | 11 | $902 |
| 09 22 16 | Bottom track, 3-5/8" 20ga, Types A + D · A-101 · tags 1, 4 | 240 | LF | $276 | 0 | $0 |
| 09 22 16 | Deflection track, slotted 3-5/8" 20ga, top of to-deck walls · A-101 · tags 1, 4 | 240 | LF | $588 | 5 | $410 |
| 09 22 16 | Track, 3-5/8" 25ga, top + bottom, Type B · A-101 · tag 2 | 596 | LF | $429 | 0 | $0 |
| 09 22 16 | Track, 2-1/2" 25ga, top + bottom, Type C · A-101 · tag 3 | 128 | LF | $79 | 0 | $0 |
| 09 22 16 | Kickers to structure @ 4'-0" o.c., Types B + C · A-101 · tags 2, 3 | 90 | EA | $405 | 13.5 | $1,107 |
| 09 22 16 | Door openings, double 20ga jambs + header (HM frames by Div 08) · A-101 · tag 6 | 15 | EA | $630 | 15 | $1,230 |
| 09 22 16 | Backing, 20ga plate: grab bars, casework, wall-mounted TVs · A-101 · tag 7 | 120 | LF | $390 | 7 | $574 |
| ACOUSTIC INSULATION + SEALANT · 09 81 00 | ||||||
| 09 81 00 | Sound batts, 3-1/2" unfaced, full height, Types A, B, D · A-101 · tags 1, 2, 4 | 6,191 | SF | $4,829 | 37 | $3,034 |
| 07 92 00 | Acoustical sealant, head + base both sides, Types A, B · A-101 · tags 1, 2 | 1,928 | LF | $617 | 19.5 | $1,599 |
| GYPSUM BOARD · 09 29 00 | ||||||
| 09 29 00 | 5/8" Type X, walls · 324 sheets 4x12 incl. 10% waste · A-101 · tags 1–5 | 14,110 | SF | $7,258 | 226 | $18,532 |
| 09 29 00 | 5/8" Type X moisture-resistant, wet side · 24 sheets 4x12 incl. 10% · A-101 · tag 4 | 1,008 | SF | $756 | 18 | $1,476 |
| 09 29 00 | 5/8" sag-resistant ceiling board · 13 sheets 4x12 incl. 12% · RCP-101 · tags 8, 9 | 544 | SF | $322 | 14 | $1,148 |
| 09 22 26 | Drywall suspension grid, restroom ceilings · RCP-101 · tag 8 | 384 | SF | $1,018 | 8.5 | $697 |
| 09 22 16 | Soffit framing, 3-5/8" 25ga, 2'-0" box at reception · RCP-101 · tag 9 | 64 | LF | $608 | 11.5 | $943 |
| 09 29 00 | Screws + fasteners allowance ($0.035/SF of board) · — | 15,662 | SF | $548 | 0 | $0 |
| TRIM + FINISH · 09 29 00 (GA-214 finish levels) | ||||||
| 09 29 00 | Corner bead, metal, outside corners · A-101 | 210 | LF | $122 | 4 | $328 |
| 09 29 00 | L-bead at window returns and mullions · A-101 · tag 5 | 140 | LF | $91 | 3.5 | $287 |
| 09 29 00 | Control joints, zinc, 30'-0" max spacing · A-101 | 48 | LF | $77 | 2 | $164 |
| 09 29 00 | Level 4 finish, tape + 3 coats + sand (mud/tape allowance) · A-101 · RCP-101 | 12,830 | SF | $1,411 | 218 | $17,876 |
| 09 29 00 | Level 5 finish, skim coat, reception + conference walls · A-101 · tag 10 | 432 | SF | $82 | 12 | $984 |
| 09 29 00 | Level 1 fire-tape, above ceiling on to-deck walls · A-101 · tags 1, 4 | 2,400 | SF | $96 | 9.5 | $779 |
| ACOUSTICAL CEILINGS · 09 51 13 | ||||||
| 09 51 13 | Suspension grid, 15/16" exposed tee, 2x2, intermediate duty · RCP-101 · tag 11 | 5,210 | SF | $7,555 | 73 | $5,986 |
| 09 51 13 | ACT, 2x2 mineral fiber, square tegular, NRC 0.70 · RCP-101 · tag 11 | 5,210 | SF | $11,202 | 36.5 | $2,993 |
| 09 51 13 | Wall angle, perimeter molding · RCP-101 · tag 11 | 820 | LF | $394 | 10 | $820 |
| GENERAL | ||||||
| 01 74 00 | Layout, stocking, material handling and daily cleanup · — | 1 | LS | $0 | 40 | $3,280 |
| Totals | $45,229 | 871.5 | $71,463 | |||
Labor at $82/hr loaded (sample rate). Partition LF measured through door openings. Board SF is net wall area; sheet counts include waste.
| Step | What happens |
|---|---|
| 1. Send your plans | Email PDF drawings and specs to bids@squareandlevelfl.com and include your bid due date. |
| 2. Fixed quote in 2 hours | We reply with the price and delivery time before any work starts. |
| 3. Estimate delivered | Marked-up sheets, takeoff and Excel estimate, usually within 24–48 hours. |
| 4. One revision included | Tell us what changed and we update the numbers. |
This is a sample created to show our format. The project, quantities and prices are illustrative, not a client job or a quote.